Unicorn Project Status Report
Status Report Date: 04/07/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.0
Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen
Sales Representative: Laurie Chase
Major Activities/ Meetings Completed
Weekly Call: Tuesday 2 p.m.
Library continues to work on policies
Adam worked with Sam and Steve to complete a training area test.
Activities/ Meetings Scheduled for Next Week
First week of on site training
No Weekly call
Outstanding Issues
Monitor, keyboard and mouse should be received at the library on Friday or Monday.
Project Status:
Event | Status | Completion Date | Notes: |
---|---|---|---|
Schedule | Completed | 01/24/06 | |
Hardware Install | On Schedule | Damon will be going to the library the week of April 17th to complete the hardware installation. | |
Software | On Schedule | ||
Policies/Profiling | In Process | ||
Data | On Schedule | Test load – 3/12/06 Production load 3/14/07 | |
SirsiDynix Training | On Schedule | First week of training is April 10-14 | |
Go Live | On Schedule |