SirsiDynix Project Manager's Weekly Project Status Report #7

SirsiDynix logo


Unicorn Project Status Report

Status Report Date: 04/07/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.0

Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen
Sales Representative: Laurie Chase

Major Activities/ Meetings Completed
Weekly Call: Tuesday 2 p.m.
Library continues to work on policies
Adam worked with Sam and Steve to complete a training area test.

Activities/ Meetings Scheduled for Next Week
First week of on site training
No Weekly call

Outstanding Issues
Monitor, keyboard and mouse should be received at the library on Friday or Monday.

Project Status:

EventStatusCompletion DateNotes:
ScheduleCompleted01/24/06
Hardware InstallOn ScheduleDamon will be going to the library the week of April 17th to complete the hardware installation.
SoftwareOn Schedule
Policies/ProfilingIn Process
DataOn ScheduleTest load – 3/12/06 Production load 3/14/07
SirsiDynix TrainingOn ScheduleFirst week of training is April 10-14
Go LiveOn Schedule