Thursday, January 19, 2006

Implementation Timeline

Latest revision: June 19, 2007

The Sirsi ILS implementation formally got underway on January 3, 2006, with SirsiDynix's ordering of new servers for the Library.

An implementation schedule has been projected with a planned "go live" date of June 14, 2007 for the new system.

The following timeline shows the major tasks and milestones ahead. As the project progresses, dates will change, and tasks and events will be noted with a checkmark (a) when they are completed or have passed. This timeline will be updated regularly.

(Please note that this timeline updates the draft schedule distributed at the October 26, 2005 Implementation Management Team meeting.)

2006

January 3
The Computer Hardware & Wireless Network Team begins to assess and prepare the server environment using the "Pre-Installation Guide to Configuring Hardware."a
Production, Test, Enterprise Portal Solution/Rooms, and Web servers and racks are ordered. a

January 23
A wireless survey is conducted onsite by SirsiDynix. a

January 30
DRA Classic reports are run on our existing system. a

February
The Computer Hardware & Wireless Network Team returns the "Pre-Installation Guide to Configuring Hardware" to SirsiDynix.a

February 7-9
Our Sirsi Unicorn Project Manager, Amanda Little, meets with members of the Unicorn Policy Creation and Data Migration Teams during a Pre-Installation Visit. a

February 10
The Unicorn Policy Creation Team begins work on Unicorn policy creation. a

February 13
The Training & Staff Development Team returns a completed copy of a "Training Preparation Guide" to SirsiDynix. a
Bibliographic, item, authority, patron, circulation, serials, and acquisitions data is extracted from the DRA Classic system. a

February 27
Members of the Training and Staff Development Team and other key staff will participate in a “Meet the Trainer” conference call to be introduced to the SirsiDynix trainer. a
A SirsiDynix integration consultant will ship the Unicorn client (Workflows) CD. a

March 1
The Enterprise Portal Solution (EPS) Team begins work with the SirsiDynix SingleSearch/Resolver/Rooms/EPS Project Manager, Carol Stennett.a

March 13-17
The Computer Hardware & Wireless Network Team receives the new Production, Test, Enterprise Portal Solution/Rooms, and Web servers and racks.a

March 20-24
The operating system for the new servers is installed and configured. A SirsiDynix Client /Server Delivery Specialist will complete this work onsite. a

March 27-31
The Training & Staff Development Team distributes training materials and reviews the training documentation. a
The Computer Hardware & Wireless Network Team configures the network to allow all necessary connections for EPS/Rooms/SingleSearch/Resolver. a

April 3-7
The Computer Hardware & Wireless Network Team sets up the training room, including setting up workstations, installing the Unicorn client software, and attaching printers. a

April 10-14
First week of onsite training, conducted with generic software, policies, and data. a

April 18
Members of the Implementation Management Team will participate in a conference call with a SirsiDynix consultant to discuss Demand Management. (Note: This is only a conference call to determine if the Library will use Demand Management , and will need the onsite summit.) a

May 1
The Training & Staff Development Team begins developing the training plan for all library staff. a

May 10
The SirsiDynix Unicorn Policy Creation Team returns the following completed documents:

Policy Excel Worksheetsa
Classic Guide to Loading Dataa
Data Mapping Chartsa
Rooms/EPS (OPAC) questionnairea

May 15-19
The SirsiDynix integration consultant will remotely install a generic training system with generic data on the test server. a
SirsiDynix staff install Rooms software (including purchased Rooms modules) configure it with Unicorn, and configure the OPAC (test data at this time). a

May 18-19
Quality control checks are completed on the test server by the SirsiDynix Software Application Specialist. a

May 22-24
Quality control checks are completed on the test server by the SirsiDynix Project Manager and Trainer. a

May 22-26
The SirsiDynix Project Manager reviews the completed policies. a
Members of the Data Migration Team participate in a conference call to review the Classic Guide to Loading Data and completed data mapping charts with the SirsiDynix Project Manager and Data Conversion Consultant. a

May 30-June 2
A SirsiDynix Client/Server Delivery Specialist enters the policies into the software configuration. a

June 5-9
The Client/Server Delivery Specialist will install Unicorn remotely on the production server. a

June 19-23
Quality control checks completed on the production server by a Software Application Specialist. a

June 19-23
Data preparation for test data load onto the production server. a

June 20
Conference call with SirsiDynix SureStart Consultant Diane Cunningham to discuss the cataloging and circulation summits in July. a

July 10-11
The Cataloging Team participates in a Cataloging onsite summit with SirsiDynix consultant Diane Cunningham. a

Paul Gahn and Steve Foster attend Unicorn Administration training and Unix Server Administration training at a date to be determined during this period. a

July 10-August 4
SirsiDynix loads and indexes data for test load on the production server. a

July 17-18
The Circulation Team participates in a Circulation onsite summit with SirsiDynix consultant Diane Cunningham. a

July 19-20
The Unicorn Policy Creation Team participates in a Demand Management onsite summit with SirsiDynix consultant Diane Cunningham. a

July 27
SirsiDynix conducts a 1-day session of onsite Rooms Builder training for the EPS Team. a

August 7-11
The Data Migration Team participates in a conference call with a consultant to discuss how to review a test data load. a

August 14-18
The SirsiDynix Project Manager and Data Consultant complete quality control checks. a

August 16-17
SirsiDynix Consulting Services conducts a 2-day onsite Rooms Planning Workshop for members of the EPS Team. The workshop includes Personas Training, Taxonomy Exploration, and Taxonomy Development. a

August 25
Members of the EPS Team participate in an introductory call regarding Central Search. a

August 28
The production server is turned over to the Library to begin data review. a
SirsiDynix provides a data reporting table.a

August 28-September 8
MPLIC returns the completed connection spreadsheet and completed customization form to Serials Solutions and SirsiDynix.a

August 28-January 29, 2007
This is the Data Migration Team's data review period for all data types.
(Note: Data review will take place on the production server.)

August 28-September 1
Second week of onsite training.a

September 8-29
Serials Solutions works with content providers regarding authentication.a

September 11
SirsiDynix upgrades the Unicorn production server from version GL3.0 to GL3.1.a
SirsiDynix orders the PocketCirc devices.a

After Sept. 11
SirsiDynix copies the production server to the test server.a

Mid-September-October
MPLIC staff installs WorkFlows client on the staff computers that will be conducting data review and training. a

September 21
The Data Migration and Cataloging Teams participate in a conference call with a SirsiDynix consultant to discuss indexing.a

September 25
9XX training is conducted for the Acquisitions and Cataloging Teams.a

September 27
EDI training is conducted for the Acquisitions team.a

October 1 - 6
Connection information is uploaded to Serials Solutions servers. a

October 10-12
The Acquisitions Team participates in an Acquisitions onsite summit with a SirsiDynix consultant (2 days). a

October 9-13
Serials Solutions tests connections. a

October 16
SirsiDynix orders the SVA server. a

October 17-18
Two days of onsite training by Sirsi (formerly "Week 3"). a
Serials Solutions implements customizations. a

October 23
SirsiDynix and Serials Solutions coordinate the sending of the Central Search URL and instructions. a

October 23-27 ­
The Computer Hardware & Wireless Network Team installs the phone lines for SVA. a

October 30-November 3
The Library's Unicorn system administrators (Paul Gahn, Steve Foster) participate in a conference call with a SirsiDynix consultant to discuss reports. a
MPLIC conducts a review for additional changes to or questions about the initial Central Search installation. a

November 7-8
The Serials & Gov Docs Team participates in a Serials /Government documents onsite summit with a SirsiDynix consultant (2 days). a

November 13-17
MPLIC begins working on the Marcive GPO records download, bib and item record creation process. a

November 14
The Collection Exchange Team participates in a WebEx seesion with a SirsiDynix consultant.a

November 16
SVA server is received at SirsiDynix and configured. a

December 4
The Computer Hardware & Wireless Network Team and the Unicorn system administrators confirm the installation of phone lines for SVA. a

December 12
The EPS Team and Serials Solutions have a Client Center/AMS walk-through for Article Linker. a

Late December (approximately)
The EPS Team completes and returns the Article Linker customization forms. a

December - January
The EPS Team completes the referring sources and target setup for Article Linker.a
SirsiDynix orders dialogic boards for the SVA server.a
The dialogic boards for the SVA server are received at SirsiDynix and the SVA server is configured.a
SVA software is installed by SirsiDynix. a
SirsiDynix ships the SVA server to MPLIC. a
The SVA server is received and installed on network by the Computer Hardware & Wireless Network Team and the Unicorn system administrators. a

2007

January
The Computer Hardware & Wireless Network Team and the Unicorn system administrators review the SVA Configuration User’s Guide and SVA training webinar. a

January 12
MPLIC returns questionnaires for SIP and NCIP setup.a

January (and ongoing)
Content creation for EPS/Rooms, including input of taxonomy, creation of Rooms, and addition of content to content modules.
Proofing and editing of EPS/Rooms content, including addition of desired graphics, branding, and remaining aesthetics.
Review and testing of EPS/Rooms.

February 7
SirsiDynix, the Computer Hardware & Wireless Network Team and the Unicorn system administrators hold a phone consultation to review the SVA configuration file.a

February
The Computer Hardware & Wireless Network Team and the Unicorn system administrators begin SVA testing.a
The Unicorn system administrator with the EPS Team manages the SIP2 interface setup for the 3M self check at East Shelby Library and the Overdrive E-audio books service.a


March-May
The Hardware & Wireless Network Team and the Unicorn system administrator begin installation and testing of configuration, test Smartport, and test peripheral devices. They consider barcode readers, inventory scanners, receipt printers, spine label printer, notice printers, self check machines. (Pending installation of Patch Cluster 5.) a

April 30
Final date for the Unicorn Policy Creation Team to make changes to the Unicorn policy file.a
The Data Migration Team returns the final Data Loading Guide and revised Data Mapping Charts.a

May (tentative)
SirsiDynix upgrades EPS/Rooms to version 2.2.a
A quality control check is done for EPS/Rooms 2.2.a
Serials Solutions makes final adjustments to Article Linker customizations.a
SirsiDynix integrates Central Search and Article Linker in EPS/Rooms, following the upgrade to version 2.2. a
SirsiDynix conducts a second day of onsite Rooms Builder training, using version 2.2.

May 1
System training for reference staff begins.a

May 3

System training for Circulation staff begins.a

May 8
The Data Migration Team has a Final Data Call with the SirsiDynix Project Manager and Data Conversion Consultant.a

May 11
Last day for MPLIC to use the DRA Classic system Cataloging module.a

May 11 or sooner
The DRA Classic system administrator (Paul Gahn) returns the completed Classic Bridge questionnaire.a

May 13
SirsiDynix does the final extract of bibs, items and authorities from Classic server. (Note: This activity does take place on a Sunday. )a

At about this time, the Unicorn system administrators begin having regular calls with the SirsiDynix SureStart consultant in preparation for Go Live.a

May 14 - 25
SirsiDynix loads bibs, items and authorities to the Unicorn production server.a

May 25
Last day for MPLIC to use the Classic system Acquisitions Vendor and Serials modules.a

May 25 (tentative)
SirsiDynix does the final extract of acquisitions data from the Classic system.a

May 29
MPLIC begins review of bibs, items and authorities, and resumes cataloging at its discretion. Unicorn services may be interrupted from time to time during additional loads scheduled and due to the loading of additional data, server response may be slowed.a

May 29 - 30
SirsiDynix loads acquisitions data (vendor records only) to the Unicorn production server.a

May 30
SirsiDynix does the final extract of serials data from Classic system.a

May 31
MPLIC verifies that all staff computers have the Workflows Client loaded. a

May 31 - June 5
SirsiDynix loads serials data to the Unicorn production server.a


June 6
SirsiDynix does the final extract of patron and circulation data from the Classic system.a

Last day for MPLIC to use the Classic system Circulation module.a


June 7
Last day of system training for Circulation staff.a


June 7 - 13
SirsiDynix loads patron and circulation records onto the Unicorn production server.
MPLIC uses Classic Bridge for circulation while patron and circulation data is being loaded.a


June 12 - 16
The SureStart consultant is onsite for Go Live.a


June 13
MPLIC does a full system backup of the Unicorn production system.a

SirsiDynix loads Classic Bridge circulation transactions onto Unicorn production system.a
Note: This activity will happen overnight.

June 14
Go Live on Unicorn circulation module, SVA, and Rooms/Central Search/Article Linker/EPS..a

Dates are yet to be determined (or are in flux) for the following tasks/milestones:

Copy of the Unicorn production server to the test server.
Launch of the Collection Exchange project.
The SirsiDynix Secure Resources project.
The Bluesocket Wireless Network Solution project.
API training.
Begin planning for the Hyperion and Director's Station projects.
Begin testing Collection Agency reports.
SirsiDynix manages setup for LincPlus bindery project.

No comments: