Status Report Date: 06/23/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.0
Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen, Diane Cunningham
Sales Representative: Laurie Chase
Major Activities/ Meetings Completed
Weekly call: Tuesday at 2 p.m.
Diane joined the weekly call to discuss the cataloging and circulation summits that will take place in July.
Quality control checks completed on the production server.
Jenny has completed the data preparation.
Laurie is working with Steve on how best for the library to receive Unicorn admin training.
Activities/ Meetings Scheduled for Next Week
Weekly call: Tuesday at 2 p.m.
Continue practicing using the test server.
Outstanding Issues
Project Status:
Event | Status | Completion Date | Notes: |
---|---|---|---|
Schedule | Completed | 01/24/06 | |
Hardware Install | Completed | 04/18/06 | |
Software | Completed | 06/02/06 | |
Policies/Profiling | Completed | 05/25/06 | |
Data | On Schedule | Test load to be completed 8/10/06. Production load 3/14/07 | |
SirsiDynix Training | On Schedule | Second week of training is August 28-31. | |
Go Live | On Schedule |