Unicorn Project Status Report
Note: New and/or revised information is now italicized.
Status Report Date: 06/02/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.0
Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen, Diane Cunningham
Sales Representative: Laurie Chase
Major Activities/ Meetings Completed
Weekly call: Tuesday at 2 p.m.
Serials and Acquisitions data mapping charts will be provided on Friday.
Policies were entered.
Oracle was installed on the production server.
Software on the production server was installed.
Laurie is working on Serials Solutions and Admin training pricing that might be need for contract modifications.
Activities/ Meetings Scheduled for Next Week
Weekly call: Tuesday at 2 p.m.
Outstanding Issues
Project Status:
Event | Status | Completion Date | Notes: |
---|---|---|---|
Schedule | Completed | 01/24/06 | |
Hardware Install | Completed | 04/18/06 | |
Software | Completed | 06/02/06 | |
Policies/Profiling | Completed | 05/25/06 | |
Data | On Schedule | Test load – 6/23/06 Production load 3/14/07 | |
SirsiDynix Training | On Schedule | Second week of training is August 28-31. | |
Go Live | On Schedule |
No Internal Updates