Unicorn Project Status Report
Note: New and/or revised information is italicized.
Status Report Date: 08/25/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.0
Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen, Diane Cunningham
Sales Representative: Laurie Chase
Major Activities/ Meetings Completed
Introduction to Central Search Call on Friday at 1pm Central.
Amanda provided a Central Search demo site to the library.
Amanda has requested from the scheduling department time in November to work with Margaret on Collection Exchange.
Amanda has been providing answers for Rooms/EPS questions.
Library can begin using the production sever for data review.
Amanda is checking on the status of the contract mod for training.
Alan asked for details about the Rooms/EPS content.
Activities/ Meetings Scheduled for Next Week
Begin looking at the test data load on the production server.
Second week of on-site training.
Work on connection and customization spreadsheet for Central Search.
Outstanding Issues
Project Status:
Event | Status | Completion Date | Notes: |
---|---|---|---|
Schedule | Completed | 01/24/06 | |
Hardware Install | Completed | 04/18/06 | |
Software | Completed | 06/02/06 | |
Policies/Profiling | Completed | 05/25/06 | |
Data | On Schedule | Test load to be completed 8/10/06. Production load 3/14/07 | |
SirsiDynix Training | On Schedule | Second week of training is August 28-Sept. 1. | |
Go Live | On Schedule |