Unicorn Project Status Report
Note: New and/or revised information is italicized.
Status Report Date: 10/20/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.1
Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen, Diane Cunningham
Sales Representative: Laurie Chase
Major Activities/ Meetings Completed
Jennifer was onsite for training.
Continue data review on the production system.
Weekly call: Thursday.
Amanda is following up on questions from weekly call.
Activities/ Meetings Scheduled for Next Week
No weekly call .
Data review on the production server.
Site to work on installing phone lines for SVA.
Amanda to order SVA server.
Outstanding Issues
Project Status:
Event | Status | Completion Date | Notes: |
---|---|---|---|
Schedule | Completed | 01/24/06 | |
Hardware Install | Completed | 04/18/06 | |
Software | Completed | 06/02/06 | |
Policies/Profiling | Completed | 05/25/06 | |
Data | On Schedule | Production load 3/14/07 | |
SirsiDynix Training | On Schedule | ||
Go Live | On Schedule |