Unicorn Project Status Report
Note: New and/or revised information is italicized.
Status Report Date: 10/06/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.1
Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen, Diane Cunningham
Sales Representative: Laurie Chase
Major Activities/ Meetings Completed
Amanda continues to look into questions about training for materials booking and Hyperion.
Damon and Paul continue to work together.
Continue data review on the production system.
Activities/ Meetings Scheduled for Next Week
Weekly Call: Tuesday
Data review on the production server.
Pocket Circ devices will be received no later than October 12th.
Acquisitions onsite summit with Diane.
Outstanding Issues
Project Status:
Event | Status | Completion Date | Notes: |
---|---|---|---|
Schedule | Completed | 01/24/06 | |
Hardware Install | Completed | 04/18/06 | |
Software | Completed | 06/02/06 | |
Policies/Profiling | Completed | 05/25/06 | |
Data | On Schedule | Production load 3/14/07 | |
SirsiDynix Training | On Schedule | 3rd training will start Oct. 17 | |
Go Live | On Schedule |