Unicorn Project Status Report
Note: Since the weekly reports have developed to a point where the majority of items are new, italics are no longer being used to identify new information.
Status Report Date: 1/26/07
Site Name: Memphis Public Library (24 libraries)
Client Contact: Alan Stewart
Go-Live Date: 6/14/07
Software Release: GL 3.1
Go-Live: Yes
SureStart: 9 months
Project Manager: Jeannie Peters
Implementation Team: Damon Hunter (CS), Jenny Hendrickson (DC), Patty Suessen (TR), Pam Tejes (SC)
Sales Representative: Laurie Chase/Bill Kessler/Gena Wilhite
Major Activities/ Meetings Completed
• Weekly Call
• Revised schedule was sent to Memphis with new go live date of 6/14/07.
• Jeannie is investigating possible dates that billable systems configuration work can be done.
• Jennifer submitted her responses to the most recent data issues log from Memphis.
• Jeannie is pursuing why the advanced limits EPS/Rooms specifications work has not been done.
• Steve McCafferty returned Memphis’ contract to Alan with responses.
• Jeannie clarified that Memphis has purchased NCIP which is described in the contracted as an Enhanced LINCPlus Interface.
• Memphis asked if EPS/Rooms 2.2 release is still scheduled for 3/1.
• Memphis asked Jeannie to find out how EPS/Rooms incidents are referencing their Unicorn server – through the IP or domain name.
Activities/ Meetings Scheduled for Next Week
• Weekly Call on Tuesday at 2:00 Central time.
• Data review on the production server
• Continuing work on EPS/Rooms
Outstanding Issues
• Waiting on permanent fix to Oracle memory leak.
Project Status:
Event | Status | Completion Date | Notes: |
---|---|---|---|
Schedule | Completed | 01/24/06 | |
Hardware Install | Completed | 04/18/06 | |
Software | Completed | 06/02/06 | |
Policies/Profiling | Completed | 05/25/06 | |
Data | On Schedule | ||
SirsiDynix Training | On Schedule | ||
Go Live | On Schedule | Postponed to 6/14/07. |