Unicorn Project Status Report
Status Report Date: 3/30/07
Site Name: Memphis Public Library (24 libraries)
Client Contact: Alan Stewart
Go-Live Date: 6/14/07
Software Release: GL 3.1
Go-Live: Yes
SureStart: 9 months
Project Manager: Jeannie Peters
Implementation Team: Damon Hunter (CS), Jenny Hendrickson (DC), Patty Suessen (TR), Pam Tejes (SC)
Sales Representative: Gena Wilhite
Major Activities/ Meetings Completed
• A username and password was sent to Alan so that he can access Hyperion on the example site that was sent to him.
• Bill Ellett responded to a follow-up Classic Bridge question.
• Gina Wilhite is leaving SirsiDynix and will no longer be the Sales Rep. for Memphis.
• A list of contract items yet to be delivered was sent to Steve Foster.
• Steve Foster’s questions regarding maintenance were sent to Pam LaPier. He will be getting in touch with her for assistance in getting the information he needs.
Activities/ Meetings Scheduled for Next Week
• Weekly Call on Tuesday at 2:00 Central time. The conference number will be used for all future calls.
• Continuing data review on the production server
• Continuing work on EPS/Rooms
Outstanding Issues
• Memphis is waiting on Damon’s return to complete IBM printer installation.
• Memphis continues to work with Norm on correcting the error with the custom automated backup script for their EPS/Rooms server.
Project Status:
Event | Status | Completion Date | Notes: |
---|---|---|---|
Schedule | Completed | 01/24/06 | |
Hardware Install | Completed | 04/18/06 | |
Software | Completed | 06/02/06 | |
Policies/Profiling | Completed | 05/25/06 | |
Data | On Schedule | ||
SirsiDynix Training | On Schedule | ||
Go Live | On Schedule | Postponed to 6/14/07. |