Sunday, April 30, 2006

SirsiDynix Project Manager's Weekly Unicorn Project Status Report #10

SirsiDynix logo


Unicorn Project Status Report

Status Report Date: 04/28/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.0

Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen, Diane Cunningham
Sales Representative: Laurie Chase

Major Activities/ Meetings Completed
Library continues to work on policies.
Amanda is working with Diane and the library to schedule the demand management summit.
Continue using the training system for practice.

Activities/ Meetings Scheduled for Next Week
Weekly call: Tuesday at 2 p.m.
Policy call with Diane.
Begin developing a staff training plan.
Continue using the training system for practice.

Outstanding Issues

Project Status:

EventStatusCompletion DateNotes:
ScheduleCompleted01/24/06

Hardware Install

Completed04/18/06
SoftwareOn Schedule
Policies/ProfilingIn ProcessPolicies are due May 10
DataOn ScheduleTest load – 6/23/06 Production load 3/14/07
SirsiDynix TrainingOn ScheduleSecond week of training is August 28-31.
Go LiveOn Schedule

Rooms/EPS Project Manager's Weekly Project Status Report #6

SirsiDynix logo


Project Status Report
Rooms/EPS and SingleSearch


Site Name: Memphis Public Library
Report Date: April 24th, 2006
Project Team:
• Unicorn Project Manager – Amanda Little
• Rooms/EPS Project Manager – Carol Stennett
• Client/Server Delivery Specialist – Craig Lawrence
• Product Specialist, SingleSearch – Adrianne Peters

Important Deadlines:
• March 15th, 2007 – Go Live on All Products

Tasks Completed
• Rooms/EPS Consulting Workshop scheduled for June 21st and 22nd
o Assigned Consultant – Charlotte Olson, Consulting Services
• Rooms Builder Training Scheduled for July 27th
o Assigned Trainer – Andrea Downing, Education Support

Upcoming/Outstanding Tasks for Week of April 24
• Address any new questions during conference call on Tuesday, April 25th

Friday, April 21, 2006

SirsiDynix Project Manager's Weekly Project Status Report #9

SirsiDynix logo


Unicorn Project Status Report

Status Report Date: 04/21/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.0

Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen, Diane Cunningham
Sales Representative: Laurie Chase

Major Activities/ Meetings Completed
Weekly call: Tuesday at 2p.m.. Carol joined the call to answer any Rooms/EPS questions. Diane also joined the call to discuss demand management.
Call with Paul on Thursday to discuss ways to shorten the circulation map.
Damon was on-site Monday and Tuesday to complete the hardware installation.
Information on returning the keyboard, monitor and mouse has been provided to Steve and Alan.

Activities/ Meetings Scheduled for Next Week
Weekly call: Tuesday at 2 p.m.
Continue working on policies.
Begin developing a staff training plan.
Continue using the training system for practice.

Outstanding Issues

Project Status:

EventStatusCompletion DateNotes:
ScheduleCompleted01/24/06

Hardware Install

Completed04/18/06
SoftwareOn Schedule
Policies/ProfilingIn ProcessPolicies are due May 10
DataOn ScheduleTest load – 6/23/06 Production load 3/14/07
SirsiDynix TrainingOn ScheduleSecond week of training is August 28-31.
Go LiveOn Schedule

Wednesday, April 19, 2006

Holds update: MPLIC to use Demand Management

On April 18, the Unicorn Policy File Team and several other MPLIC staff members participated in a conference call with our SirsiDynix Unicorn Project Manager, Amanda Little, and a SirsiDynix SureStart Consultant, Diane Cunningham, to discuss Demand Management. Demand Management is a feature of Unicorn that permits libraries to more closely manage the placement and fulfillment of holds.

Based on a review of the decisions reached by this same staff group on February 27, Diane advised us to use Demand Management for our implementation of the Unicorn Holds function.

A one-day Demand Management Summit will be added to the Implementation Timeline following a review of the schedule by both MPLIC and SirsiDynix.

Tuesday, April 18, 2006

Rooms/EPS Project Manager's Weekly Project Status Report #5

SirsiDynix logo


Project Status Report
Rooms/EPS and SingleSearch


Site Name: Memphis Public Library
Report Date: April 17th, 2006
Project Team:
• Unicorn Project Manager – Amanda Little
• Rooms/EPS Project Manager – Carol Stennett
• Client/Server Delivery Specialist – Craig Lawrence
• Product Specialist, SingleSearch – Adrianne Peters

Important Deadlines:
• May 15th, 2007 – Go Live on All Products

Tasks Completed
• Rooms/EPS Consulting Workshop scheduled for June 21st and 22nd
o Assigned Consultant – Charlotte Olson, Consulting Services
• Rooms Builder Training Scheduled for July 27th
o Assigned Trainer – Andrea Downing, Education Support

Upcoming/Outstanding Tasks for Week of April 17
• Address any new questions during conference call on Tuesday, April 18th

Friday, April 14, 2006

SirsiDynix Project Manager's Weekly Status Report #8

SirsiDynix logo


Unicorn Project Status Report

Status Report Date: 04/14/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.0

Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen
Sales Representative: Laurie Chase

Major Activities/ Meetings Completed
No Weekly Call
Paul sent a draft set of policies for review.
First week of on-site training

Activities/ Meetings Scheduled for Next Week
Weekly call: Tuesday at 2 p.m. Topic for discussion is demand management.
Damon on site Monday to complete the hardware installation.
Test system will be installed on the test server by Damon next week.

Outstanding Issues

Project Status:

EventStatusCompletion DateNotes:
ScheduleCompleted01/24/06
Hardware InstallOn ScheduleDamon will be going to the library the week of April 17th to complete the hardware installation.
SoftwareOn Schedule
Policies/ProfilingIn ProcessPolicies are due May 10
DataOn ScheduleTest load – 6/23/06 Production load 3/14/07
SirsiDynix TrainingOn ScheduleSecond week of training is August 28-31.
Go LiveOn Schedule

Thursday, April 13, 2006

Guide to the Enterprise Portal Solution, Part 3 (or, What are Rooms?)

Genealogy & Family History Room screen shot
Many references to the Enterprise Portal Solution, on this blog as well as in SirsiDynix's documentation, refer to "Rooms/EPS," or sometimes "EPS/Rooms." While EPS and Rooms are not the exact same thing, they are closely integrated, and the EPS interface is dependent on the Rooms technology platform.

The Rooms concept adopts the idea of physical spaces in libraries which house specific collections or services (think the Memphis Room, or the Popular Library at Central) and extends this as a metaphor for virtual spaces on the Library's web site. This is in fact very similar to what our web site already offers with subject-specific areas like the Virtual Health Information Center; however, Sirsi's Rooms offer a degree of integration between web sites, databases, and the library catalog which we have not had before.

The basic Rooms/EPS installation comes with a Reading Room, which offers users a virtual location to learn about book clubs as well as offering other readers' advisory information, and an Audiences Room, with special areas for Businesses, Kids, and Adult Learners/ESL. MPLIC has also purchased the Rooms Starter Pack, which includes an additional 10 Rooms: Careers & Employment, Parenting, Genealogy, Entertainment, Reference, Personal Finance & Investing, Travel & Tourism, Home Improvement, Family Health & Fitness, and Food & Drink. Each of these Rooms features content selected and organized by library and content professionals at SirsiDynix.

Even more significantly for MPLIC, however, we are acquiring the Rooms Builder, a Web-based tool that will allow our library staff to edit the "starter" Rooms, adding and subtracting sites and other content, as well as to create new Rooms, all without requiring knowledge of HTML. MPLIC web content providers will be able to pick and choose from the Sirsi Rooms content to supplement our current content, most of which will be migrated over from our current site to the Rooms environment. We also anticipate that staff will be able to update their content themselves without the intervention of the Computer Resources Librarian or Electronic Services Coordinator. (And, incidentally, we are not required to use the term "Rooms" on our site if we choose not to do so.)

It's probably easier to understand Rooms through experience rather than by explanation. I encourage you to take a test drive of the EPS/Rooms interface, either through the links above or through either of these links to the home pages for two Sirsi demonstration sites (which are almost but not quite identical):

(Please note that these sites are for staff use only.)

Next: What is SingleSearch?

Image courtesy SirsiDynix

Wednesday, April 12, 2006

Rooms/EPS Project Manager's Weekly Project Status Report #4

SirsiDynix logo


Project Status Report
Rooms/EPS and SingleSearch


Site Name: Memphis Public Library
Report Date: April 10th, 2006
Project Team:
• Unicorn Project Manager – Amanda Little
• Rooms/EPS Project Manager – Carol Stennett
• Client/Server Delivery Specialist – Craig Lawrence
• Product Specialist, SingleSearch – Adrianne Peters

Important Deadlines:
• May 15th, 2007 – Go Live on All Products

Tasks Completed
• Rooms/EPS Consulting Workshop scheduled for June 21st and 22nd
o Assigned Consultant – Charlotte Olson, Consulting Services

Upcoming/Outstanding Tasks for Week
• Confirm Rooms server has been configured with OS by end of week - Memphis
• Check on port opening progress – any questions? – Memphis
• Schedule Rooms/EPS Builder Training

Tuesday, April 11, 2006

"Opening Day" for Sirsi Training

Workflows screen shot
On Monday, April 10, a number of MPLIC staff got their first hands-on experience with the Unicorn staff client, Workflows (a screenshot of which is shown here), and the public catalog interface, the Enterprise Portal Solution.

38 staff members will be attending this week's classes at Central, which include Essential Skills for Workflows and EPS, Circulation, and Cataloging. These sessions (along with additional onsite training scheduled for August, October, and December) will form the foundation for our systemwide training as well as providing members of the Sirsi implementation teams with background information that will help us make decisions about customizing Unicorn to meet our needs.

I would like to encourage staff members who have questions, concerns, or observations to share after having been through Sirsi training to use the Comments feature of this blog to share them with me and the other members of the Implementation Management Team.

For more information about Sirsi training, read this post from February 22.

Image courtesy SirsiDynix

Friday, April 07, 2006

SirsiDynix Project Manager's Weekly Project Status Report #7

SirsiDynix logo


Unicorn Project Status Report

Status Report Date: 04/07/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.0

Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen
Sales Representative: Laurie Chase

Major Activities/ Meetings Completed
Weekly Call: Tuesday 2 p.m.
Library continues to work on policies
Adam worked with Sam and Steve to complete a training area test.

Activities/ Meetings Scheduled for Next Week
First week of on site training
No Weekly call

Outstanding Issues
Monitor, keyboard and mouse should be received at the library on Friday or Monday.

Project Status:

EventStatusCompletion DateNotes:
ScheduleCompleted01/24/06
Hardware InstallOn ScheduleDamon will be going to the library the week of April 17th to complete the hardware installation.
SoftwareOn Schedule
Policies/ProfilingIn Process
DataOn ScheduleTest load – 3/12/06 Production load 3/14/07
SirsiDynix TrainingOn ScheduleFirst week of training is April 10-14
Go LiveOn Schedule

Tuesday, April 04, 2006

Rooms/EPS Project Manager's Weekly Project Status Report #3

SirsiDynix logo


Project Status Report
Rooms/EPS and SingleSearch


Site Name: Memphis Public Library
Report Date: April 3rd, 2006
Project Team:
• Unicorn Project Manager – Amanda Little
• Rooms/EPS Project Manager – Carol Stennett
• Client/Server Delivery Specialist – Craig Lawrence
• Product Specialist, SingleSearch – Adrianne Peters

Important Deadlines:
• May 15th, 2007 – Go Live on All Products

Tasks Completed
• Rooms workshop and builder training dates sent out
• First draft of schedule reviewed
• Second draft sent on March 16th

Upcoming/Outstanding Tasks for Week
• Confirm Rooms server has been configured with OS by end of week - Memphis
• Check on port opening progress – any questions? – Memphis
• Schedule training dates
• Questions to answer:
o Workshop and Training Room Details – The individual on the Rooms team that can answer this is out of the office and will be back on Wednesday. I’ll send the answers along ASAP no later than Wednesday end of the day.

Friday, March 31, 2006

SirsiDynix Project Manager's Weekly Project Status Report #6

SirsiDynix logo


Unicorn Project Status Report

Status Report Date: 03/31/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.0

Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen
Sales Representative: Laurie Chase

Major Activities/ Meetings Completed
Weekly Call: Tuesdays 2:00 CST
Library continues to work on policies
E-learning logins provided
Library continues to work with Carol on EPS/Rooms

Activities/ Meetings Scheduled for Next Week
Damon will contact Steve to walk through the installation of Workflows and completed a workstation test.
Install Workflows on all training computers.
Weekly call scheduled for Tuesday April 4th at 2pm.

Project Status
EventDateStatusNotes:
Schedule01/24/06Accepted
Policies/ProfilingIn Progress
DataOn Schedule
TrainingOn ScheduleFirst week of training is scheduled for April 10-14
Hardware InstallDamon will be going to the library the week of April 17th to complete the hardware installation.
SoftwareOn Schedule
Go Live03/15/07On Schedule

Thursday, March 30, 2006

Guide to the Enterprise Portal Solution, Part 2 (or, What is a portal, anyway?)

The name of Sirsi's new public interface incorporates several concepts, including web portals in general, and more specifically enterprise and library portals.

In the broadest sense, a portal is simply a Web site that offers a broad array of resources and services, such as search engines, news headlines, e-mail, discussion groups, and shopping. Yahoo, MSN, and AOL are popular examples of such portals, which many users set as the starting page for their Web browser. Somewhat more narrowly, a portal such as MyYahoo takes the concept further by allowing users to customize their own Internet start page according to their own needs and preferences – displaying only their local news and weather, latest scores from their favorite teams, daily price quotes for the stocks they own, and perhaps a few feeds from blogs they follow.

The concept of the enterprise information portal developed in the context of the corporate Intranet. Such a portal integrates an organization’s electronic data and services into a single user-customizable environment. Each member of the organization can have their own unique web site with access to all of the information and services they commonly need to do their work.

EPS screen
The library portal applies this idea to the library world. The library portal has been described as “an information hub” (a familiar concept for MPLIC!) -- a single user interface for access to the wide variety of information resources both within and outside of the library. In addition to some level of personalization or customization, library portals usually include federated searching -- also known as metasearching, or broadcast searching -- which allows customers to search all of the library’s online resources – the catalog, specialized databases, and even the Web – with a single query.

More reading about library web portals:
Abram, Stephen. "The Shop Window: Compelling and Dynamic Library Portals," SirsiDynix OneSource, December 2005.
Boss, Richard. "Library Portals (PLA Tech Notes)," March, 2005.

Next: What are “Rooms?”

Image courtesy of SirsiDynix.

Wednesday, March 29, 2006

Rooms/EPS Project Manager's Weekly Project Status Report #2

SirsiDynix logo



Project Status Report
Rooms/EPS and SingleSearch


Site Name: Memphis Public Library
Report Date: March 27th, 2006
Project Team:
Unicorn Project Manager – Amanda Little
Rooms/EPS Project Manager – Carol Stennett
Client/Server Delivery Specialist – Craig Lawrence
Product Specialist, SingleSearch – Adrianne Peters

Important Deadlines:
May 15th, 2007 – Go Live on All Products

Tasks Completed
Rooms workshop and builder training dates sent out
First draft of schedule reviewed
Second draft sent on March 16th

Upcoming/Outstanding Tasks for Week of March 20th
Confirm Rooms server has been configured with OS by end of week - Memphis
Check on port opening progress – any questions? – Memphis
Schedule training dates
Questions to answer:

  • Can we define the display order for the search limit options (Item types, locations, libraries) (like we can for Pickup libraries)? Or is the display sorted by the:
    *60 character Description?
    *10 character Policy name?
    Or is it the order entered in the Unicorn policy file (delivereds, then our item types)
    Answer: Carol is checking on this
  • Why is the text running off the page at Oxnard Public Library?
    Answer: Oxnard is still at version 2.0. We are upgrading them to version 2.1 next week. We haven’t been able to identify exactly why the text is running off like it is in certain pages. We have not seen this on any sites that we have installed at version 2.1 build 355, which is the official released build of version 2.1

Friday, March 24, 2006

Sirsi Implementation Teams: The Data Migration Team

The Data Migration Team is responsible for making certain that all of the borrower records, circulation information, cataloging data, and all other information in our DRA Classic system is transferred properly to our new Unicorn ILS.

This week, this team met jointly with the Unicorn Policy File Team to discuss issues in Unicorn policy creation and to review an initial draft of the Unicorn policy file developed by Paul Gahn.

Role of the Data Migration Team:

  • To coordinate data migration from the DRA Classic ILS to the Sirsi Unicorn ILS
  • To identify the requirements for data conversion and transfer
  • To identify the requirements for reports and management information
  • To identify the requirements for and to coordinate the delivery of staff training
  • To identify and make recommendations on potential workflow changes
Reporting:

Reports to the Sirsi Implementation Management Team

Membership:

Chair – Paul Gahn (Automated Services)
Ann Delphin (Central Circulation)
Wang-Ying Glasgow (Serials/Gov. Docs.)
Deborah Powell (Cataloging)
Cindy Soenksen (Acquisitions)

    SirsiDynix Project Manager's Weekly Project Status Report #5

    SirsiDynix logo


    Project Status Report

    Site Name: Memphis Public Library
    Date: 03/24/06

    Project Manager: Amanda Little
    Sales Representative: Laurie Chase
    Client Contact: Steve Foster and Alan Stewart

    Major Activities/ Meetings Completed
    Weekly call on Tuesday at 2 p.m.
    Library continuing to working on policies
    Adam and Damon were on-site to install the production , test ,and Rooms/EPS server

    Activities/ Meetings Scheduled for Next Week
    Continue working on policies
    Call schedule for Tuesday March 28th at 2 p.m.
    Receive training manuals

    Project Status
    1. Access –
    2. Hardware – During the on-site hardware installed it was discovered that the rails for the production server and cables for the KVM switch were missing. Both items have been ordered, and the rails have arrived on-site. Printers are on order.
    3. Software –
    4. Policies – Library is continuing to working on policies
    5. Data – A successful test data extraction has been completed.
    6. Training – The first week of training is scheduled for April 10-14
    7. Schedule – All activities are on schedule.

    Thursday, March 23, 2006

    Sirsi Unicorn & DRA Classic Compared

    Damone Virgilio has developed an informative Powerpoint slide show comparing terms we use in DRA Classic with their equivalents. This presentation, which made its debut at the Circulation Services Users Group Meeting in March, has been posted to the Intranet so it can be accessed by all staff. You will find a permanent link to the presentation on the Staff Development Intranet page as well as in this blog's list of links.

    When you click on the link you will have the option of saving the Powerpoint file to your hard drive or opening it in the browser. If you choose the latter, the presentation will open in slide show mode. To advance through the presentation, either click the left mouse button or press the Page Down key on your keyboard. To return to the Intranet or blog page you were on, click the "Back" button in the browser.

    Wednesday, March 22, 2006

    Sirsi Implementation Teams: The Computer Hardware & Wireless Network Team

    The Computer Hardware & Wireless Network Team is busy this week offering coordination and assistance as SirsiDynix technicians install new servers in the Computer Room.

    Role of the Computer Hardware & Wireless Network Team:

    • To coordinate the installation of computer and network hardware as required to implement the Sirsi ILS and wireless network
    • To identify the requirements for reports and management information
    • To identify the requirements for and to coordinate the delivery of staff training
    • To identify and make recommendations on potential workflow change

    Reporting:

    Reports to the Sirsi Implementation Management Team

    Membership:

    (All members are Automated Services staff.)

    Chair – Sam Ivy
    Steve Foster
    Paul Gahn
    Mike Gordon
    Sidino Beverly
    John Dooley
    Deshone Marshall
    Jerry Walker

    Tuesday, March 21, 2006

    Rooms/EPS Project Manager's Weekly Project Status Report #1

    SirsiDynix logo


    Project Status Report
    Rooms/EPS and SingleSearch


    Site Name: Memphis Public Library
    Report Date: March 20th, 2006
    Project Team:
    • Unicorn Project Manager – Amanda Little
    • Rooms/EPS Project Manager – Carol Stennett
    • Client/Server Delivery Specialist – Craig Lawrence
    • Product Specialist, SingleSearch – Adrianne Peters

    Important Deadlines:
    • May 15th, 2007 – Go Live on All Products

    Tasks Completed
    • First draft of schedule reviewed
    • Second draft sent on March 16th


    Upcoming/Outstanding Tasks for Week of March 20th
    • Confirm Rooms server has been configured with OS by end of week - Memphis
    • Check on port opening progress – any questions? – Memphis
    • Send Available Training Dates - Carol

    Monday, March 20, 2006

    Guide to the Enterprise Portal Solution, Part I (or, Whatever happened to iBistro?)

    iBistro screen shotStaff who have been involved in planning for the migration to a new ILS for the last couple of years, or who have just been interested observers, will remember the term iBistro as the name for Sirsi's Web catalog interface. Many of us have been impressed with the enhanced features and content available in iBistro, with book jacket art, synopses, and reviews provided for many titles. As more recent communications have referred to the Web catalog interface for the new ILS as the Enterprise Portal Solution, or EPS, some of you may be wondering what the difference is, or what has become of iBistro.

    IBistro (or, as it is implemented in acdemic libraries, iLink) is a web catalog interface that functions well as a stand-alone resource that is part of a library web site. SirsiDynix continues to sell iBistro but is no longer actively developing it. In 2005 the company introduced its new public interface, the Enterprise Portal Solution, which was intended to integrate the catalog with a library's other online resources to become a single public interface for a library's web site.

    EPS screenWhile it is possible to implement EPS as a stand-alone catalog interface, it has been designed to work in conjunction with other SirsiDynix products such as Rooms and SingleSearch to function as a portal to all of a library's web resources. However, the enhanced content and other features that staff have appreciated in iBistro implementations such as those listed in the Sirsi Unicorn OPAC examples post will be part of EPS as well.

    Next: What is a "portal," anyway?

    Images courtesy of SirsiDynix.