Unicorn Project Status Report
Note: New and/or revised information is italicized.
Status Report Date: 07/21/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.0
Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen, Diane Cunningham
Sales Representative: Laurie Chase
Major Activities/ Meetings Completed
No weekly call.
Diane was on site for summits this week.
Jenny is working on loading and indexing data on the production server.
Activities/ Meetings Scheduled for Next Week
Weekly call Tuesday at 2pm.
Jenny will begin loading and indexing data.
Continue practicing using the test server.
Outstanding Issues
Project Status:
Event | Status | Completion Date | Notes: |
---|---|---|---|
Schedule | Completed | 01/24/06 | |
Hardware Install | Completed | 04/18/06 | |
Software | Completed | 06/02/06 | |
Policies/Profiling | Completed | 05/25/06 | |
Data | On Schedule | Test load to be completed 8/10/06. Production load 3/14/07 | |
SirsiDynix Training | On Schedule | Second week of training is August 28-31. | |
Go Live | On Schedule |