Unicorn Project Status Report
Note: New and/or revised information is italicized.
Status Report Date: 07/07/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.0
Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen, Diane Cunningham
Sales Representative: Laurie Chase
Major Activities/ Meetings Completed
No weekly call.
Training coupon issued and Paul has signed up for training.
Activities/ Meetings Scheduled for Next Week
No weekly call.
Jenny will begin loading and indexing data.
Continue practicing using the test server.
Diane will be on site for the cataloging summit.
Outstanding Issues
Project Status:
Event | Status | Completion Date | Notes: |
---|---|---|---|
Schedule | Completed | 01/24/06 | |
Hardware Install | Completed | 04/18/06 | |
Software | Completed | 06/02/06 | |
Policies/Profiling | Completed | 05/25/06 | |
Data | On Schedule | Test load to be completed 8/10/06. Production load 3/14/07 | |
SirsiDynix Training | On Schedule | Second week of training is August 28-31. | |
Go Live | On Schedule |