Unicorn Project Status Report
Note: New and/or revised information is italicized.
Status Report Date: 09/08/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.0
Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen, Diane Cunningham
Sales Representative: Laurie Chase
Major Activities/ Meetings Completed
Weekly Call: Tuesday
Alan working on Central Search Forms.
Amanda provided additional information about Hyperion project.
Library to continue data review and staff training.
Activities/ Meetings Scheduled for Next Week
Weekly Call: Tuesday
Upgrade to GL3.1 on Monday.
Copy of production to test server on Wednesday.
Amanda to gather more information about Director’s Station project.
Outstanding Issues
Project Status:
Event | Status | Completion Date | Notes: |
---|---|---|---|
Schedule | Completed | 01/24/06 | |
Hardware Install | Completed | 04/18/06 | |
Software | Completed | 06/02/06 | |
Policies/Profiling | Completed | 05/25/06 | |
Data | On Schedule | Production load 3/14/07 | |
SirsiDynix Training | On Schedule | ||
Go Live | On Schedule |