Unicorn Project Status Report
Note: New and/or revised information is italicized.
Status Report Date: 09/14/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.0
Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen, Diane Cunningham
Sales Representative: Laurie Chase
Major Activities/ Meetings Completed
Weekly Call: Tuesday
Steve is having issues with getting a backup completed of the production server; issue has been sent to Damon.
Production server was upgraded to GL 3.1 on Monday
Damon copied the production server to the test server on Wednesday, and is working to resolve any issues.
Amanda sent contract addendum for training.
Activities/ Meetings Scheduled for Next Week
Weekly Call: Tuesday
Data review on the production server
Conference call to discuss indexing
Outstanding Issues
Project Status:
Event | Status | Completion Date | Notes: |
---|---|---|---|
Schedule | Completed | 01/24/06 | |
Hardware Install | Completed | 04/18/06 | |
Software | Completed | 06/02/06 | |
Policies/Profiling | Completed | 05/25/06 | |
Data | On Schedule | Production load 3/14/07 | |
SirsiDynix Training | On Schedule | ||
Go Live | On Schedule |