Tuesday, July 25, 2006

SirsiDynix Project Manager's Weekly Unicorn Project Status Report #19

SirsiDynix logo


Unicorn Project Status Report

Note: New and/or revised information is italicized.

Status Report Date: 07/14/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.0

Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen, Diane Cunningham
Sales Representative: Laurie Chase

Major Activities/ Meetings Completed
No weekly call.
Diane on site for the cataloging summit.
Jenny is working on loading data on the production sever.


Activities/ Meetings Scheduled for Next Week
No weekly call.
Jenny will begin loading and indexing data.
Continue practicing using the test server.
Diane will be on site for the circulation and demand management summits.

Outstanding Issues

Project Status:


EventStatusCompletion DateNotes:
ScheduleCompleted01/24/06

Hardware Install

Completed04/18/06
SoftwareCompleted06/02/06
Policies/ProfilingCompleted05/25/06

DataOn Schedule

Test load to be completed 8/10/06. Production load 3/14/07

SirsiDynix TrainingOn Schedule
Second week of training is August 28-31.
Go LiveOn Schedule

No comments: