Tuesday, July 25, 2006

SirsiDynix Project Manager's Weekly Unicorn Project Status Report #20

SirsiDynix logo


Unicorn Project Status Report

Note: New and/or revised information is italicized.

Status Report Date: 07/21/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.0

Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen, Diane Cunningham
Sales Representative: Laurie Chase

Major Activities/ Meetings Completed
No weekly call.
Diane was on site for summits this week.
Jenny is working on loading and indexing data on the production server.

Activities/ Meetings Scheduled for Next Week
Weekly call Tuesday at 2pm.
Jenny will begin loading and indexing data.
Continue practicing using the test server.

Outstanding Issues

Project Status:


EventStatusCompletion DateNotes:
ScheduleCompleted01/24/06

Hardware Install

Completed04/18/06
SoftwareCompleted06/02/06
Policies/ProfilingCompleted05/25/06

DataOn Schedule

Test load to be completed 8/10/06. Production load 3/14/07

SirsiDynix TrainingOn Schedule
Second week of training is August 28-31.
Go LiveOn Schedule