Unicorn Project Status Report
Note: New and/or revised information is italicized.
Status Report Date: 08/18/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.0
Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen, Diane Cunningham
Sales Representative: Laurie Chase
Major Activities/ Meetings Completed
Weekly call: Tuesday.
Amanda and a trainer have completed quality control checks on the production server.
Amanda has requested from the scheduling department time in November to work with Margaret on Collection Exchange.
Amanda updated the schedule.
Upgrade to GL3.1 has been schedule for September 11th.
Pam was onsite for the Rooms workshop August 16-17.
Activities/ Meetings Scheduled for Next Week
No weekly call.
Outstanding Issues
Get library logo put into Rooms.
Project Status:
Event | Status | Completion Date | Notes: |
---|---|---|---|
Schedule | Completed | 01/24/06 | |
Hardware Install | Completed | 04/18/06 | |
Software | Completed | 06/02/06 | |
Policies/Profiling | Completed | 05/25/06 | |
Data | On Schedule | Test load to be completed 8/10/06. Production load 3/14/07 | |
SirsiDynix Training | On Schedule | Second week of training is August 28-31. | |
Go Live | On Schedule |