SirsiDynix Project Manager's Weekly Status Report #23

SirsiDynix logo


Unicorn Project Status Report

Note: New and/or revised information is italicized.

Status Report Date: 08/18/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.0

Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen, Diane Cunningham
Sales Representative: Laurie Chase

Major Activities/ Meetings Completed
Weekly call: Tuesday.
Amanda and a trainer have completed quality control checks on the production server.
Amanda has requested from the scheduling department time in November to work with Margaret on Collection Exchange.
Amanda updated the schedule.
Upgrade to GL3.1 has been schedule for September 11th.
Pam was onsite for the Rooms workshop August 16-17.

Activities/ Meetings Scheduled for Next Week
No weekly call.

Outstanding Issues
Get library logo put into Rooms.

Project Status:

EventStatusCompletion DateNotes:
ScheduleCompleted01/24/06

Hardware Install

Completed04/18/06
SoftwareCompleted06/02/06
Policies/ProfilingCompleted05/25/06

DataOn Schedule

Test load to be completed 8/10/06. Production load 3/14/07

SirsiDynix TrainingOn Schedule
Second week of training is August 28-31.
Go LiveOn Schedule