SirsiDynix Project Manager's Weekly Status Report #21

SirsiDynix logo


Unicorn Project Status Report

Note: New and/or revised information is italicized.

Status Report Date: 07/27/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.0

Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen, Diane Cunningham
Sales Representative: Laurie Chase

Major Activities/ Meetings Completed
Weekly call: Tuesday.
Thomas Leimkuehler joined the weekly call to discuss Rooms Builder training.
Thursday -- Rooms Builder training.

Jenny is working on loading and indexing data on the production server.

Activities/ Meetings Scheduled for Next Week
Weekly call Tuesday at 2pm.
Jenny will finish up the test load on the production server.
Continue practicing using the test server.

Outstanding Issues

Project Status:
EventStatusCompletion DateNotes:
ScheduleCompleted01/24/06

Hardware Install

Completed04/18/06
SoftwareCompleted06/02/06
Policies/ProfilingCompleted05/25/06

DataOn Schedule

Test load to be completed 8/10/06. Production load 3/14/07

SirsiDynix TrainingOn Schedule
Second week of training is August 28-31.
Go LiveOn Schedule