SirsiDynix Project Manager's Weekly Status Report #25

SirsiDynix logo


Unicorn Project Status Report

Note: New and/or revised information is italicized.

Status Report Date: 09/08/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.0

Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen, Diane Cunningham
Sales Representative: Laurie Chase

Major Activities/ Meetings Completed
Weekly Call: Tuesday
Alan working on Central Search Forms.
Amanda provided additional information about Hyperion project.
Library to continue data review and staff training.

Activities/ Meetings Scheduled for Next Week
Weekly Call: Tuesday
Upgrade to GL3.1 on Monday.
Copy of production to test server on Wednesday.
Amanda to gather more information about Director’s Station project.


Outstanding Issues

Project Status:
EventStatusCompletion DateNotes:
ScheduleCompleted01/24/06

Hardware Install

Completed04/18/06
SoftwareCompleted06/02/06
Policies/ProfilingCompleted05/25/06

DataOn Schedule

Production load 3/14/07

SirsiDynix TrainingOn Schedule
Go LiveOn Schedule