Friday, October 13, 2006

SirsiDynix Project Manager's Weekly Status Report #30

SirsiDynix logo


Unicorn Project Status Report

Note: New and/or revised information is italicized.

Status Report Date: 10/13/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.1

Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen, Diane Cunningham
Sales Representative: Laurie Chase

Major Activities/ Meetings Completed
Diane was onsite for the Acquisitions summit.
Continue data review on the production system.
Amanda gathered information about EPS administration class.
Pocket Circ devices arrived.
Amanda sent updated project schedule.
Paul turned in an updated data investigation log.

Activities/ Meetings Scheduled for Next Week
Weekly Call: Tuesday
Data review on the production server.
3rd week of on site training.

Outstanding Issues

Project Status:

EventStatusCompletion DateNotes:
ScheduleCompleted01/24/06

Hardware Install

Completed04/18/06
SoftwareCompleted06/02/06
Policies/ProfilingCompleted05/25/06

DataOn Schedule

Production load 3/14/07

SirsiDynix TrainingOn Schedule
3rd training will start Oct. 17
Go LiveOn Schedule

No comments: