Unicorn Project Status Report

Note: New and/or revised information is italicized.

Status Report Date: 10/20/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.1

Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen, Diane Cunningham
Sales Representative: Laurie Chase

Major Activities/ Meetings Completed
Jennifer was onsite for training.
Continue data review on the production system.
Weekly call: Thursday.
Amanda is following up on questions from weekly call.

Activities/ Meetings Scheduled for Next Week
No weekly call .
Data review on the production server.
Site to work on installing phone lines for SVA.
Amanda to order SVA server.


Outstanding Issues

Project Status:


EventStatusCompletion DateNotes:
ScheduleCompleted01/24/06

Hardware Install

Completed04/18/06
SoftwareCompleted06/02/06
Policies/ProfilingCompleted05/25/06

DataOn Schedule

Production load 3/14/07

SirsiDynix TrainingOn Schedule
Go LiveOn Schedule