SirsiDynix Project Manager's Weekly Status Report #40

SirsiDynix logo


Unicorn Project Status Report

Note: New and/or revised information is italicized.

Status Report Date: 1/12/07
Site Name: Memphis Public Library (24 libraries)
Client Contact: Alan Stewart
Go-Live Date: 03/15/07
Software Release: GL 3.1
Go-Live: Yes
SureStart: 9 months

Project Manager: Jeannie Peters
Implementation Team: Damon Hunter (CS), Jenny Hendrickson (DC), Patty Suessen (TR), Pam Tejes (SC)
Sales Representative: Laurie Chase/Bill Kessler

Major Activities/ Meetings Completed
• Weekly Call
Jeannie sent Alan and Paul information regarding the 260 as an alternate search in response to a searching issue experienced earlier in the project.
Memphis has decided to delay installation of their LINCPlus until 3-6 months after their go live.
• Bill Kessler sent Memphis a quote for some billable custom server configuration.
• Pam Tejes was onsite January 9-11 for a consulting visit.
• Jeannie is researching LINCPlus questions from Memphis.
• The IBM system printer has arrived onsite and it will be installed this week.
• A request has been sent to Jennifer Hendrickson for her to respond to Memphis’ question regarding migrating call numbers with mixed case.
• Belinda Hamm has been requested to coordinate any needed HIR with Memphis if needed for the SIP2 installation.
• A request has been sent to Belinda Hamm to confirm whether or not she can do her SVA call with Memphis on February 5. Their SVA is to be installed in February and this needs to be put on her schedule with specific dates.
• Jeannie is working on updating the timeline/schedule and will return this to Memphis the week of January 15.
• Memphis has notified Margaret Pelfrey that they will delay Collection Exchange training and implementation until sometime after they go live. They will use the Recirculate functionality for their Large Print Rotating Collection.

Activities/ Meetings Scheduled for Next Week
• Weekly Call on Thursday [1/18] at 10 MT, 11 CT.
• Data review on the production server
• Continuing work on EPS/Rooms

Outstanding Issues
Kristiana Burk was on the weekly call with Memphis. For now, all EPS/Rooms [questions] will go to her and Alex Feng rather than Client Care in order to have them responded to more quickly. Kristiana also stated that we hope that 2.2 will be released on March 1 and that we will work with Memphis on the installation of it. We will do a WebEx session with them to go over the differences between 2.2 and 2.1. She stressed that Memphis’ EPS/Rooms issues are a priority for us and she offered to go there for a half day onsite visit to talk over their concerns and get their feedback.

Project Status:

EventStatusCompletion DateNotes:
ScheduleCompleted01/24/06

Hardware Install

Completed04/18/06
SoftwareCompleted06/02/06
Policies/ProfilingCompleted05/25/06

DataOn Schedule

Production load 3/14/07

SirsiDynix TrainingOn Schedule

Go LiveOn Schedule