Unicorn Project Status Report
Status Report Date: 4/6/07
Site Name: Memphis Public Library (24 libraries)
Client Contact: Alan Stewart
Go-Live Date: 6/14/07
Software Release: GL 3.1
Go-Live: Yes
SureStart: 9 months
Project Manager: Jeannie Peters
Implementation Team: Damon Hunter (CS), Jenny Hendrickson (DC), Patty Suessen (TR), Pam Tejes (SC)
Sales Representative: Gena Wilhite
Major Activities/ Meetings Completed
• Steve Foster contacted Pam LaPier for assistance in determining years 2 – 5 for hardware maintenance, software maintenance, and subscription fees associated with the contract between SirsiDynix and the City of Memphis
• Alex Feng has been working with Alan this week on some EPS/Rooms questions
• Paul resumed work with Damon on getting the IBM Infoprint configured as the system printer
• Paul also questioned Damon as to why the Solaris daylight savings time patch had been applied to the test server but not production.
Activities/ Meetings Scheduled for Next Week
• Weekly Call on Tuesday at 2:00 Central time. The conference number will be used for all future calls.
• Continuing data review on the production server
• Continuing work on EPS/Rooms
Outstanding Issues
• Memphis continues to work with Norm Curl on correcting the error with the custom automated backup script for their EPS/Rooms server.
Project Status:
Event | Status | Completion Date | Notes: |
---|---|---|---|
Schedule | Completed | 01/24/06 | |
Hardware Install | Completed | 04/18/06 | |
Software | Completed | 06/02/06 | |
Policies/Profiling | Completed | 05/25/06 | |
Data | On Schedule | ||
SirsiDynix Training | On Schedule | ||
Go Live | On Schedule | Postponed to 6/14/07. |