Tuesday, April 17, 2007

SirsiDynix Project Manager's Weekly Status Report #52

SirsiDynix logo


Unicorn Project Status Report

Status Report Date: 4/13/07
Site Name: Memphis Public Library (24 libraries)
Client Contact: Alan Stewart
Go-Live Date: 6/14/07
Software Release: GL 3.1
Go-Live: Yes
SureStart: 9 months

Project Manager: Jeannie Peters
Implementation Team: Damon Hunter (CS), Jenny Hendrickson (DC), Patty Suessen (TR), Pam Tejes (SC)
Sales Representative: Gena Wilhite

Major Activities/ Meetings Completed

• Weekly Call

• Three data issues were submitted to Jenny Hendrickson and she responded to them.

• Alex Feng is continuing discussions with Alan regarding EPS/Rooms questions and issues.

Activities/ Meetings Scheduled for Next Week


• Weekly Call on Tuesday at 2:00 Central time. The conference number will be used for all future calls.

• Continuing data review on the production server

• Continuing work on EPS/Rooms

Outstanding Issues

• Memphis continues to work with Norm Curl on correcting the error with the custom automated backup script for their EPS/Rooms server.

• Waiting on a response from Damon regarding why the Solaris daylight savings time patch had been applied to the test server but not production.

• Paul is continuing work with Damon on getting the IBM Infoprint configured as the system printer.

• Steve Foster is continuing working with Pam LaPier on determining maintenance for years 2 – 5 for hardware maintenance, software maintenance, and subscription fees associated with the contract between SirsiDynix and the City of Memphis

Project Status:

EventStatusCompletion DateNotes:
ScheduleCompleted01/24/06

Hardware Install

Completed04/18/06
SoftwareCompleted06/02/06
Policies/ProfilingCompleted05/25/06

DataOn Schedule


SirsiDynix TrainingOn Schedule

Go LiveOn Schedule
Postponed to 6/14/07.