SirsiDynix Project Manager's Weekly Status Report #27

SirsiDynix logo


Unicorn Project Status Report

Note: New and/or revised information is italicized.

Status Report Date: 09/21/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.1

Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen, Diane Cunningham
Sales Representative: Laurie Chase

Major Activities/ Meetings Completed
Weekly Call: Tuesday
Amanda is looking into questions about training for materials booking and Hyperion.
Damon is continuing to help Paul with questions about the copy over and issues from the copy over.
Conference call with Diane to discuss indexing on Friday.


Activities/ Meetings Scheduled for Next Week
Weekly Call: Tuesday
Data review on the production server.
Staff will attend 9XX and EDI training.

Outstanding Issues

Project Status:

EventStatusCompletion DateNotes:
ScheduleCompleted01/24/06

Hardware Install

Completed04/18/06
SoftwareCompleted06/02/06
Policies/ProfilingCompleted05/25/06

DataOn Schedule

Production load 3/14/07

SirsiDynix TrainingOn Schedule
Go LiveOn Schedule

2 comments:

Anonymous said...

Are you adding self-check machines with the upgrade? If yes - what self-check machine are you using.

Are you adding PC reservation system - Envisionware?

Are you adding credit card payment option for patrons?

Alan Stewart said...

We have one self-check machine currently operating at our East Shelby branch (3M). We have a public PC print management system (Pharos software via Xerox Global Services) and we are interested in implementing a PC signup/reservation system in the future. We're interested in exploring an online commerce aspect as well. However, none of these projects are part of our current ILS migration project.