SirsiDynix Project Manager's Weekly Status Report #32

SirsiDynix logo


Unicorn Project Status Report

Note: New and/or revised information is italicized.

Status Report Date: 11/3/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.1

Project Manager: Jeannie Peters
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen, Diane Cunningham
Sales Representative: Laurie Chase

Major Activities/ Meetings Completed
Weekly call.
Jeannie was introduced as the new project manager.
Alan continues to work with Central Search.
Jenny is working on requested data changes.


Activities/ Meetings Scheduled for Next Week
Weekly call.
Data review on the production server.
Diane onsite next week for Serials/Gov Doc Summit.

Outstanding Issues

Project Status:
EventStatusCompletion DateNotes:
ScheduleCompleted01/24/06

Hardware Install

Completed04/18/06
SoftwareCompleted06/02/06
Policies/ProfilingCompleted05/25/06

DataOn Schedule

Production load 3/14/07

SirsiDynix TrainingOn Schedule
Go LiveOn Schedule