SirsiDynix Project Manager's Weekly Status Report #49

SirsiDynix logo


Unicorn Project Status Report

Status Report Date: 3/23/07
Site Name: Memphis Public Library (24 libraries)
Client Contact: Alan Stewart
Go-Live Date: 6/14/07
Software Release: GL 3.1
Go-Live: Yes
SureStart: 9 months

Project Manager: Jeannie Peters
Implementation Team: Damon Hunter (CS), Jenny Hendrickson (DC), Patty Suessen (TR), Pam Tejes (SC)
Sales Representative: Gena Wilhite

Major Activities/ Meetings Completed

• Weekly Call

• Vince Jennings and Steve Foster attended this week’s call and one or both will be in attendance on most if not all of the remaining calls until go live. Vince and Steve are liaisons from the City of Memphis Office of Information Services.

• Progress continues on the IBM printer installation.

• Entitlement paperwork for the IBM printer 3 year warranty has been received from the vendor.

• Paul installed Patch Cluster 5 on the test server and has begun installing the client on workstations.

• Paul Gahn submitted another Classic Bridge discharge question that has been sent to Bill Ellett.

• SureStart calls with Pam Tejes have begun.

• Information on who Memphis will need to contact for their Sun server support and IBM printer support has been sent to them.

Activities/ Meetings Scheduled for Next Week

• Weekly Call on Tuesday at 2:00 Central time. The conference number will be used for all future calls.

• Data review on the production server.

• Continuing work on EPS/Rooms.

Outstanding Issues

• Creation and application of the automated backup script for Memphis’ EPS/Rooms server by Wayne Coop.

Project Status:

EventStatusCompletion DateNotes:
ScheduleCompleted01/24/06

Hardware Install

Completed04/18/06
SoftwareCompleted06/02/06
Policies/ProfilingCompleted05/25/06

DataOn Schedule


SirsiDynix TrainingOn Schedule

Go LiveOn Schedule
Postponed to 6/14/07.