Unicorn Project Status Report
Status Report Date: 04/14/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.0
Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen
Sales Representative: Laurie Chase
Major Activities/ Meetings Completed
No Weekly Call
Paul sent a draft set of policies for review.
First week of on-site training
Activities/ Meetings Scheduled for Next Week
Weekly call: Tuesday at 2 p.m. Topic for discussion is demand management.
Damon on site Monday to complete the hardware installation.
Test system will be installed on the test server by Damon next week.
Outstanding Issues
Project Status:
Event | Status | Completion Date | Notes: |
---|---|---|---|
Schedule | Completed | 01/24/06 | |
Hardware Install | On Schedule | Damon will be going to the library the week of April 17th to complete the hardware installation. | |
Software | On Schedule | ||
Policies/Profiling | In Process | Policies are due May 10 | |
Data | On Schedule | Test load – 6/23/06 Production load 3/14/07 | |
SirsiDynix Training | On Schedule | Second week of training is August 28-31. | |
Go Live | On Schedule |