Rooms/EPS Project Manager's Weekly Project Status Report #3

SirsiDynix logo


Project Status Report
Rooms/EPS and SingleSearch


Site Name: Memphis Public Library
Report Date: April 3rd, 2006
Project Team:
• Unicorn Project Manager – Amanda Little
• Rooms/EPS Project Manager – Carol Stennett
• Client/Server Delivery Specialist – Craig Lawrence
• Product Specialist, SingleSearch – Adrianne Peters

Important Deadlines:
• May 15th, 2007 – Go Live on All Products

Tasks Completed
• Rooms workshop and builder training dates sent out
• First draft of schedule reviewed
• Second draft sent on March 16th

Upcoming/Outstanding Tasks for Week
• Confirm Rooms server has been configured with OS by end of week - Memphis
• Check on port opening progress – any questions? – Memphis
• Schedule training dates
• Questions to answer:
o Workshop and Training Room Details – The individual on the Rooms team that can answer this is out of the office and will be back on Wednesday. I’ll send the answers along ASAP no later than Wednesday end of the day.