SirsiDynix Project Manager's Weekly Project Status Report #9

SirsiDynix logo


Unicorn Project Status Report

Status Report Date: 04/21/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.0

Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen, Diane Cunningham
Sales Representative: Laurie Chase

Major Activities/ Meetings Completed
Weekly call: Tuesday at 2p.m.. Carol joined the call to answer any Rooms/EPS questions. Diane also joined the call to discuss demand management.
Call with Paul on Thursday to discuss ways to shorten the circulation map.
Damon was on-site Monday and Tuesday to complete the hardware installation.
Information on returning the keyboard, monitor and mouse has been provided to Steve and Alan.

Activities/ Meetings Scheduled for Next Week
Weekly call: Tuesday at 2 p.m.
Continue working on policies.
Begin developing a staff training plan.
Continue using the training system for practice.

Outstanding Issues

Project Status:

EventStatusCompletion DateNotes:
ScheduleCompleted01/24/06

Hardware Install

Completed04/18/06
SoftwareOn Schedule
Policies/ProfilingIn ProcessPolicies are due May 10
DataOn ScheduleTest load – 6/23/06 Production load 3/14/07
SirsiDynix TrainingOn ScheduleSecond week of training is August 28-31.
Go LiveOn Schedule