Unicorn Project Status Report
Status Report Date: 04/21/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.0
Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen, Diane Cunningham
Sales Representative: Laurie Chase
Major Activities/ Meetings Completed
Weekly call: Tuesday at 2p.m.. Carol joined the call to answer any Rooms/EPS questions. Diane also joined the call to discuss demand management.
Call with Paul on Thursday to discuss ways to shorten the circulation map.
Damon was on-site Monday and Tuesday to complete the hardware installation.
Information on returning the keyboard, monitor and mouse has been provided to Steve and Alan.
Activities/ Meetings Scheduled for Next Week
Weekly call: Tuesday at 2 p.m.
Continue working on policies.
Begin developing a staff training plan.
Continue using the training system for practice.
Outstanding Issues
Project Status:
Event | Status | Completion Date | Notes: |
---|---|---|---|
Schedule | Completed | 01/24/06 | |
Hardware Install | Completed | 04/18/06 | |
Software | On Schedule | ||
Policies/Profiling | In Process | Policies are due May 10 | |
Data | On Schedule | Test load – 6/23/06 Production load 3/14/07 | |
SirsiDynix Training | On Schedule | Second week of training is August 28-31. | |
Go Live | On Schedule |