Tuesday, May 30, 2006

SirsiDynix Unicorn Project Manager's Weekly Project Status Report #12

SirsiDynix logo


Unicorn Project Status Report

Note: New and/or revised information is now italicized.

Status Report Date: 05/26/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.0

Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen, Diane Cunningham
Sales Representative: Laurie Chase

Major Activities/ Meetings Completed
Weekly call: Tuesday at 2 p.m.
Jenny, Data Consultant joined the weekly call to discuss data loading.
Revised data guide and policy charts were turned in.
Laurie is working on Serials Solutions.

Activities/ Meetings Scheduled for Next Week
Weekly call: Tuesday at 2 p.m.
Policies will be entered.

Outstanding Issues

Project Status:
EventStatusCompletion DateNotes:
ScheduleCompleted01/24/06

Hardware Install

Completed04/18/06
SoftwareOn schedule
Policies/ProfilingCompleted05/25/06

DataOn Schedule
Test load – 6/23/06 Production load 3/14/07
SirsiDynix TrainingOn Schedule
Second week of training is August 28-31.
Go LiveOn Schedule

No comments: