Unicorn Project Status Report
Note: New and/or revised information is now italicized.
Status Report Date: 05/26/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.0
Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen, Diane Cunningham
Sales Representative: Laurie Chase
Major Activities/ Meetings Completed
Weekly call: Tuesday at 2 p.m.
Jenny, Data Consultant joined the weekly call to discuss data loading.
Revised data guide and policy charts were turned in.
Laurie is working on Serials Solutions.
Activities/ Meetings Scheduled for Next Week
Weekly call: Tuesday at 2 p.m.
Policies will be entered.
Outstanding Issues
Project Status:
Event | Status | Completion Date | Notes: |
---|---|---|---|
Schedule | Completed | 01/24/06 | |
Hardware Install | Completed | 04/18/06 | |
Software | On schedule | ||
Policies/Profiling | Completed | 05/25/06 | |
Data | On Schedule | Test load – 6/23/06 Production load 3/14/07 | |
SirsiDynix Training | On Schedule | Second week of training is August 28-31. | |
Go Live | On Schedule |