Friday, June 02, 2006

SirsiDynix Project Manager's Weekly Unicorn Project Status Report #13

SirsiDynix logo

Unicorn Project Status Report

Note: New and/or revised information is now italicized.

Status Report Date: 06/02/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.0

Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen, Diane Cunningham
Sales Representative: Laurie Chase

Major Activities/ Meetings Completed
Weekly call: Tuesday at 2 p.m.
Serials and Acquisitions data mapping charts will be provided on Friday.
Policies were entered.
Oracle was installed on the production server.
Software on the production server was installed.
Laurie is working on Serials Solutions and Admin training pricing that might be need for contract modifications.

Activities/ Meetings Scheduled for Next Week
Weekly call: Tuesday at 2 p.m.

Outstanding Issues

Project Status:

EventStatusCompletion DateNotes:

Hardware Install


DataOn Schedule
Test load – 6/23/06 Production load 3/14/07
SirsiDynix TrainingOn Schedule
Second week of training is August 28-31.
Go LiveOn Schedule

No Internal Updates

No comments: