Friday, June 09, 2006

SirsiDynix Project Manager's Weekly Unicorn Project Status Report #14

SirsiDynix logo


Unicorn Project Status Report

Note: New and/or revised information is italicized.

Status Report Date: 06/09/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.0

Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen, Diane Cunningham
Sales Representative: Laurie Chase

Major Activities/ Meetings Completed
Weekly call: Tuesday at 2 p.m.
Jenny joined the weekly call to answer data questions.
Test data extraction will take place this weekend

Activities/ Meetings Scheduled for Next Week
Weekly call: Tuesday at 2 p.m.

Outstanding Issues

Project Status:

EventStatusCompletion DateNotes:
ScheduleCompleted01/24/06

Hardware Install

Completed04/18/06
SoftwareCompleted06/02/06
Policies/ProfilingCompleted05/25/06

DataOn Schedule
Test load – 6/23/06 Production load 3/14/07
SirsiDynix TrainingOn Schedule
Second week of training is August 28-31.
Go LiveOn Schedule