Thursday, June 29, 2006

SirsiDynix Project Manager's Weekly Unicorn Project Status Report #16

SirsiDynix logo


Unicorn Project Status Report

Note: New and/or revised information is italicized.

Status Report Date: 06/23/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.0

Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen, Diane Cunningham
Sales Representative: Laurie Chase

Major Activities/ Meetings Completed
Weekly call: Tuesday at 2 p.m.
Diane joined the weekly call to discuss the cataloging and circulation summits that will take place in July.
Quality control checks completed on the production server.
Jenny has completed the data preparation.
Laurie is working with Steve on how best for the library to receive Unicorn admin training.


Activities/ Meetings Scheduled for Next Week
Weekly call: Tuesday at 2 p.m.
Continue practicing using the test server.

Outstanding Issues

Project Status:
EventStatusCompletion DateNotes:
ScheduleCompleted01/24/06

Hardware Install

Completed04/18/06
SoftwareCompleted06/02/06
Policies/ProfilingCompleted05/25/06

DataOn Schedule

Test load to be completed 8/10/06. Production load 3/14/07

SirsiDynix TrainingOn Schedule
Second week of training is August 28-31.
Go LiveOn Schedule

No comments: