Friday, February 02, 2007

SirsiDynix Project Manager's Weekly Status Report #42

SirsiDynix logo


Unicorn Project Status Report

Note: Since the weekly reports have developed to a point where the majority of items are new, italics are no longer being used to identify new information.

Status Report Date: 1/26/07
Site Name: Memphis Public Library (24 libraries)
Client Contact: Alan Stewart
Go-Live Date: 6/14/07
Software Release: GL 3.1
Go-Live: Yes
SureStart: 9 months

Project Manager: Jeannie Peters
Implementation Team: Damon Hunter (CS), Jenny Hendrickson (DC), Patty Suessen (TR), Pam Tejes (SC)
Sales Representative: Laurie Chase/Bill Kessler/Gena Wilhite

Major Activities/ Meetings Completed

• Weekly Call

• Revised schedule was sent to Memphis with new go live date of 6/14/07.

• Jeannie is investigating possible dates that billable systems configuration work can be done.

• Jennifer submitted her responses to the most recent data issues log from Memphis.

• Jeannie is pursuing why the advanced limits EPS/Rooms specifications work has not been done.

• Steve McCafferty returned Memphis’ contract to Alan with responses.

• Jeannie clarified that Memphis has purchased NCIP which is described in the contracted as an Enhanced LINCPlus Interface.

• Memphis asked if EPS/Rooms 2.2 release is still scheduled for 3/1.

• Memphis asked Jeannie to find out how EPS/Rooms incidents are referencing their Unicorn server – through the IP or domain name.

Activities/ Meetings Scheduled for Next Week

• Weekly Call on Tuesday at 2:00 Central time.
• Data review on the production server
• Continuing work on EPS/Rooms

Outstanding Issues

• Waiting on permanent fix to Oracle memory leak.

Project Status:

EventStatusCompletion DateNotes:
ScheduleCompleted01/24/06

Hardware Install

Completed04/18/06
SoftwareCompleted06/02/06
Policies/ProfilingCompleted05/25/06

DataOn Schedule


SirsiDynix TrainingOn Schedule

Go LiveOn Schedule
Postponed to 6/14/07.