Tuesday, February 20, 2007

SirsiDynix Project Manager's Weekly Status Report #45

SirsiDynix logo


Unicorn Project Status Report

Note: Since the weekly reports have developed to a point where the majority of items are new, italics are no longer being used to identify new information.

Status Report Date: 2/16/07
Site Name: Memphis Public Library (24 libraries)
Client Contact: Alan Stewart
Go-Live Date: 6/14/07
Software Release: GL 3.1
Go-Live: Yes
SureStart: 9 months

Project Manager: Jeannie Peters
Implementation Team: Damon Hunter (CS), Jenny Hendrickson (DC), Patty Suessen (TR), Pam Tejes (SC)
Sales Representative: Gena Wilhite

Major Activities/ Meetings Completed

• Weekly Call

• A quote request has been submitted for the warranty on Memphis’ IBM printer.

• Damon has said that installing the Serial port notice printer over the network will work.

• Jeannie reviewed with Memphis a list for Memphis of all unfulfilled items in their contract.

• Craig completed his work on the advanced limits EPS/Rooms specifications.

Activities/ Meetings Scheduled for Next Week

• Weekly Call on Tuesday at 2:00 Central time.

• Data review on the production server.

• Continuing work on EPS/Rooms.

Outstanding Issues

• Jeannie contacted John Dickson to ask if he has any new information regarding the permanent fix to the Oracle memory leak problem and is waiting to hear back from him.

• Jeannie continues work with Damon on instructions for installing the IBM notice printer.

• Jeannie continues investigating how EPS/Rooms incidents are referencing their Unicorn server – through the IP or domain name.

• Norm Curl has told Jeannie that he hopes to write the automated backup scripts next week.

• Damon is continuing his investigation as to why the setdelinq report is erroring out on the test server. He has been told that this tends to happen after periods of inactivity; Monday mornings for example.

Project Status:

EventStatusCompletion DateNotes:
ScheduleCompleted01/24/06

Hardware Install

Completed04/18/06
SoftwareCompleted06/02/06
Policies/ProfilingCompleted05/25/06

DataOn Schedule


SirsiDynix TrainingOn Schedule

Go LiveOn Schedule
Postponed to 6/14/07.