SirsiDynix Project Manager's Weekly Project Status Report #6

SirsiDynix logo


Unicorn Project Status Report

Status Report Date: 03/31/2006
Site Name: Memphis Public Library (24 libraries)
Client Contact: Steve Foster
Go-Live Date: 03/15/07
Software Release: GL 3.0

Project Manager: Amanda Little
Implementation Team: Damon Hunter, Jenny Hendrickson, Patty Suessen
Sales Representative: Laurie Chase

Major Activities/ Meetings Completed
Weekly Call: Tuesdays 2:00 CST
Library continues to work on policies
E-learning logins provided
Library continues to work with Carol on EPS/Rooms

Activities/ Meetings Scheduled for Next Week
Damon will contact Steve to walk through the installation of Workflows and completed a workstation test.
Install Workflows on all training computers.
Weekly call scheduled for Tuesday April 4th at 2pm.

Project Status
EventDateStatusNotes:
Schedule01/24/06Accepted
Policies/ProfilingIn Progress
DataOn Schedule
TrainingOn ScheduleFirst week of training is scheduled for April 10-14
Hardware InstallDamon will be going to the library the week of April 17th to complete the hardware installation.
SoftwareOn Schedule
Go Live03/15/07On Schedule