Tuesday, March 21, 2006
Rooms/EPS Project Manager's Weekly Project Status Report #1
Project Status Report
Rooms/EPS and SingleSearch
Site Name: Memphis Public Library
Report Date: March 20th, 2006
Project Team:
• Unicorn Project Manager – Amanda Little
• Rooms/EPS Project Manager – Carol Stennett
• Client/Server Delivery Specialist – Craig Lawrence
• Product Specialist, SingleSearch – Adrianne Peters
Important Deadlines:
• May 15th, 2007 – Go Live on All Products
Tasks Completed
• First draft of schedule reviewed
• Second draft sent on March 16th
Upcoming/Outstanding Tasks for Week of March 20th
• Confirm Rooms server has been configured with OS by end of week - Memphis
• Check on port opening progress – any questions? – Memphis
• Send Available Training Dates - Carol
Subscribe to:
Post Comments (Atom)
No comments: