SirsiDynix Project Manager's Weekly Project Status Report #5

SirsiDynix logo


Project Status Report

Site Name: Memphis Public Library
Date: 03/24/06

Project Manager: Amanda Little
Sales Representative: Laurie Chase
Client Contact: Steve Foster and Alan Stewart

Major Activities/ Meetings Completed
Weekly call on Tuesday at 2 p.m.
Library continuing to working on policies
Adam and Damon were on-site to install the production , test ,and Rooms/EPS server

Activities/ Meetings Scheduled for Next Week
Continue working on policies
Call schedule for Tuesday March 28th at 2 p.m.
Receive training manuals

Project Status
1. Access –
2. Hardware – During the on-site hardware installed it was discovered that the rails for the production server and cables for the KVM switch were missing. Both items have been ordered, and the rails have arrived on-site. Printers are on order.
3. Software –
4. Policies – Library is continuing to working on policies
5. Data – A successful test data extraction has been completed.
6. Training – The first week of training is scheduled for April 10-14
7. Schedule – All activities are on schedule.